Enterprise · scaled across the networkBrownfield (retrofit into operating plants)

Ignition — First Enterprise SCADA

From isolated machine HMIs to one enterprise control and reporting layer

01 — Results

19+

Assets integrated in phase 1

Enterprise

Scaled beyond the pilot site

MetricBeforeAfterDelta
Control architectureIsolated OEM HMIsSingle licensed SCADA platformUnified
Assets visible0 networked19+ in phase 1+19
Stop-cause dataVerbal / anecdotalAttributed and reportedAuditable
DeploymentOne pilot lineScaled across the enterpriseStandardized

02 — Challenge

Each OEM asset ran its own HMI island. Nobody could see line state, stop counts or stop causes without walking the floor and asking.

Without shared signals there was no interlocking either: downstream stops kept flooding upstream WIP, and improvement arguments came down to opinion.

03 — My role

Program owner — architecture, standards, deployment

Timeline: Foundational platform

04 — Scope

05 — Execution

06 — Systems & technology

07 — Artifacts & evidence

08 — Key takeaways

The reporting layer sold the platform: leadership funded expansion once stop causes became numbers instead of arguments.