Anacortes, WABrownfield (equipment replacement in an operating plant)

DJM Plate Former / VMAG Portion Loader

$770K/year of raw-material giveaway removed on a $600K project

01 — Results

$770K/yr

Raw-material giveaway removed

$600K

Project cost

+17%

Throughput increase

MetricBeforeAfterDelta
Raw-material giveawayBaseline−$770K/yr$770K/yr
ThroughputBaseline line rate+17%No added labor
Die cavitiesLegacy die setExpanded die set+1 cavity
Project cost$600K installed<1 yr payback

02 — Challenge

Legacy formers were fed more product than they could form, so squeeze loss and drop-weight variation were structural.

Overfilling to protect label weight meant paying for giveaway on every patty, and throughput was capped by the die set.

03 — My role

Project manager

Timeline: Trials through startup

04 — Scope

05 — Execution

06 — Systems & technology

07 — Artifacts & evidence

08 — Key takeaways

Metering upstream beat tuning the former. The weight problem was a feed problem.